A given project has a bac 10000 pvcumulative to date 5000


A given project has a BAC = $10,000, PV(cumulative to date) = $5,000, AC(cumulative to date) = $6,000, and EV(cumulative to date) = $5,500. What is the schedule status of the project?

A. Ahead of schedule
B. Behind schedule
C. On-schedule
D. Cannot determine

 