A front-end loader is to load trucks with granular material


Question:

A front-end loader is to load trucks with granular material that has a swell factor of 15%. If the loader has a heaped capacity of 2.5 cu yd, calculate the total cycle time for the loader if it can move 40 cu yd of in-bank material in 1hr with an efficiency of 51 min/hr