A firm wishes to evaluate the performance of its


A firm wishes to evaluate the performance of its forecasting system. It uses data for the past three periods, as shown below.

            Period t          Actual At          Forecast Ft

                   1                     180                     200

                   2                     200                     190

                   3                     225                     210

Compute the following aggregate measures of forecast error: MFE, MAD, MSE, RMSE, MAPE.

Can you show step by step on how to calculate it.

Request for Solution File