A drilling machine is scheduled to be in production for 100


A drilling machine is scheduled to be in production for 100 hours but is down for 5 of those hours. The specifications for the drilling machine state that it can process 120 units in one hour. During the 95 hours that the machine was in operation, 10545 units were processed. 316 of the units were defective. What is the overall equipment effectiveness for the drilling machine? Do not enter a % sign, just put a 2 digit number.