A draw the project network b determine the slack for each


Consider the following project.

Activity                      Duration (weeks)                   Precedence Relationship

 

1                                            2                                 -

2                                            1                                 -

3                                            3                                 -

4                                            2                                 1, 2

5                                            3                                 2, 3

6                                             3                                 4, 5

7                                             1                                 -

8                                             2                                 6, 7

9                                             1                                 7

10                                           1                                 8, 9

a) Draw the project network.

b) Determine the slack for each activity

c) Identify the critical activities.

d) What is the least number of weeks required to complete the project?

Solution Preview :

Prepared by a verified Expert
Business Management: A draw the project network b determine the slack for each
Reference No:- TGS02746025

Now Priced at $20 (50% Discount)

Recommended (93%)

Rated (4.5/5)