A draw the network b what is the critical path c what is


The following represents a project that should be scheduled using CPM:

Times (DAYS)

Activity Immediate Predecessors a m b

A. - 1 3 5

B - 1 2 3

C A 1 2 3

D A 2 3 4

E B 3 4 11

F C,D 3 4 5

G D,E 1 4 6

H F,G 2 4 5

a. Draw the network.

b. What is the critical path?

c. What is the expected project completion time?

d. What is the probability of completing this project within 16 days?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A draw the network b what is the critical path c what is
Reference No:- TGS01089073

Expected delivery within 24 Hours