A construction site requires 35000 yds3 of soil in a


A construction site requires 35,000 yds^3 of soil in a compacted state with a moist unit weight of 126 pcf at a water content of 14%. if the uncompacted soil currently has a unit weight of 96 pcf and water content of 14%, what total volume of this soil is required to obtain the above volume of compacted soil? know: unit weight of water= 62.4 pcf assume Gs=2.65 hint: weight of the soil does not change due to compaction of the soil.