A computer technician arrives at work at 8am and finds a


A computer technician arrives at work at 8AM and finds a department manager delivering three malfunctioning laptop computers. The computer technician begins to repair the problems as soon as possible. The technician begins on the first computer and does not start the second computer until the first is repaired. The technician works on only one computer at a time.

The first computer is repaired by 11am

The second computer is repaired by 1pm

The thirds computer is repaired by 4pm

What is the total process velocity?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A computer technician arrives at work at 8am and finds a
Reference No:- TGS01121390

Expected delivery within 24 Hours