A compute the total project cost for each project duration


A project has 7 activities (A, B, C, D, E, F, and G). A proceeds B, C, and D. E follows C. F follows D. G follows B, E and F. Their normal time and costs are (5,9,8,7,4,6,3) and ($90,100,80,60,70,50,200). Their crash time and cost are (4,5,7,6,2,4,2) and ($120,140,120, 80,190,190,289). Compute the total direct cost for each project duration. If the indirect costs for each project duration are $450 (21 time units), $400 (20), $350(19), $300(18), $250(17) and $200 (16), (A) compute the total project cost for each project duration. (B) What duration represents the lowest total project cost? (C) What is this cost?

Please give explanation of the answer