A company produces 51 units of output per hour using 8


Question: A company produces 51 units of output per hour using 8 workers. Each worker is paid $12 per hour. Materials cost $15 for each unit of output produced. Overhead is charged at 1.2 times the labor expense. Finished units sell for $68 each. Calculate the single factor productivity measures for the following:

• Labor

• Materials

• Overhead