A company manufactures two products bubble and squeak the


A company manufactures two products bubble and squeak. The products are made from 3 materials A,B, and C; the following table shows quantities and price each material used in the products:

Product. A. B. C

Bubble. 1kg. 0.5 kg. 1.5 kg
Squeak. 0.5 kg. 2 kg. 0.5 kg
Price per kilos. £1.50. £1. £2.50

The production schedule for year 3 is as follows:

Month No. 1. 2. 3. 4-6. 7-9. 10-12

Bubble. 3000 3500. 3800. 10000. 11000. 12000
Squeak. 5000. 5500. 6000. 17000. 18000. 18000


Stock positions. A. B. C
Kg. kg. kg
Opening. 6000. 14000. 8000

Closing. 10 per cent higher in the final month of the year's consumption,the production of that 
Month being one third of the quarter's production.
You are required to prepare materials cost budget and purchasing budget for year 3. 