a company has developed a project and is


A company has developed a project and is interested in accelerating the schedule if possible. Below network diagram and tables show all information needed. Partial crashing is available.

Present Accelerated

Duration Cost Duration Cost

a 3 $100 2 $200

b 4 $ 50 3 $170

c 5 $250 4 $340

d 3 $100 cannot accelerate

e 6 $100 5 $175

f 7 $300 5 $600