A check on the project at week 12 shows that activity f is


A project consists of ten activities with estimated durations (in weeks) and dependences shown in the following table.

927_4da2f4a9-e6dd-4a4c-91fc-0b2c8c3f8c6f.png

(a) What are the estimated duration of the project and the earliest and latest times for activities?

(b) If activity B needs special equipment, when should this be hired?

(c) A check on the project at week 12 shows that activity F is running two weeks late, that activity J will now take six weeks and that the equipment for B will not arrive until week 18. How does this affect the overall project duration?