A certain electrical harness assembly job required 350


A certain electrical harness assembly job required 35.0 minutes to complete when a skilled worker did it the first time. The job will be performed to produce 100 harnesses. a) If the learning rate is 85%, what will the time be for the 10th unit and b) for the 100th unit?