A 35 kva transformer supplies a load of 12 kw at a power


A 35 kVA transformer supplies a load of 12 kW at a power factor of 0.45 lagging. Find the percentage of full load the transformer is carrying. If additional unity power factor loads are to be served with the same transformer, how many kW may be added before the transformer is at full load?