A 25kva transformer supplies a load with the following


A 25KVA transformer supplies a load with the following schedule:
8hrs-full load with 0.8 lagging power factor.
4hrs-75% full load at unity power factor.
12hrs-No load.
The transformer is energised 24hrs per day and has iron losses of350w.
The transformer has maximum efficiency at 60% full load.
With info given what is the all day efficiency of this transformer?