A 2 m high sandy fill material was placed loosely at a


A 2 m high sandy fill material was placed loosely at a relative density of 47%. Laboratory studies indicated tht the maximum and minimum void ratios of the fill material are 0.92 and 0.53, respectively. Construction specifications required that the fill be compacted to a relative density of 80%. If Gs = 2.65, determine:

a. Dry unity weight of the fill before and after compaction

b. Final height of the fill after compaction

Request for Solution File

Ask an Expert for Answer!!
Civil Engineering: A 2 m high sandy fill material was placed loosely at a
Reference No:- TGS0830615

Expected delivery within 24 Hours