A 1500-foot subdivision street is to be constructed the


A 1,500-foot subdivision street is to be constructed. The layout will be completed in three days; the fill will be brought in over the course of eight days; the compaction/grading will be completed in five days; the asphalt topping will be done in three days; and the striping will take one day to complete. Using a minimum float guideline of one day, develop a linear schedule for this project. What is the project duration if no activities are to be interrupted? Suggest ways that the duration can be shortened.