3000 widgets must be machined on workstation


3,000 widgets must be machined on workstation during week. Each widget is identical and requires a machining cycle time (Tc) of 36.5 minutes. All of the machining centres in the shop are equally capable of producing widgets in the specified cycle time. Q: How many machining centres must be devoted to widget production during the given week, if there are 90 hours of available time on each machining center?