1 calculate the npv of a project with the following cash


1. Calculate the NPV of a project with the following cash flows and a 10% discount rate:

Year                     0                 1                 2                 3                 4                 

Cash Inflows       $0             $125           $150           $200            $225

Cash Outflows   $375          $175           $100            $50              $50

From years 5 - 9, you will receive net cash inflows of $100 per year