CRITICAL RATIO

1. Calculate the critical ratios for the following activities and indicate which activities are probably on target and which need to be investigated. Comment on each activity.

Activity           Actual             Scheduled       Budgeted        Actual

                        Progress           Progress           Cost                 Cost

A                     4 days              4 days              $60                  $40

B                     3 days              2 days              $50                  $50

C                     2 days              3 days              $30                  $20

D                     1 Day              1 day               $20                  $30

E                      2 days              4 days              $25                  $25

2. Given the following information about a showroom renovation, which activities are on time, which are early, and which are behind schedule?

Activity           Budgeted cost             Actual Cost                 Critical Ratio

A                     $60                              $40                              1.0

B                     $25                              $50                              0.5

C                     $45                              $30                              1.5

D                     $20                              $20                              1.5

E                      $50                              $50                              0.67

3. Design and plot a critical ratio for a computer installation project that had planned constant, linear progress from 0 to an earned value of  200 over a 100 day duration. In fact progress for the first 20 days has been: 2, 3, 4, 6, 7, 9,12, 14, 15, 17, 20, 21,21, 22, 24, 26, 27, 29, 31, 33. What can you conclude about this project

CRITICAL RATIO

1. Calculate the critical ratios for the following activities and indicate which activities are probably on target and which need to be investigated. Comment on each activity.

Activity           Actual             Scheduled       Budgeted        Actual

                        Progress           Progress           Cost                 Cost

A                     4 days              4 days              $60                  $40

B                     3 days              2 days              $50                  $50

C                     2 days              3 days              $30                  $20

D                     1 Day              1 day               $20                  $30

E                      2 days              4 days              $25                  $25

2. Given the following information about a showroom renovation, which activities are on time, which are early, and which are behind schedule?

Activity           Budgeted cost             Actual Cost                 Critical Ratio

A                     $60                              $40                              1.0

B                     $25                              $50                              0.5

C                     $45                              $30                              1.5

D                     $20                              $20                              1.5

E                      $50                              $50                              0.67

3. Design and plot a critical ratio for a computer installation project that had planned constant, linear progress from 0 to an earned value of  200 over a 100 day duration. In fact progress for the first 20 days has been: 2, 3, 4, 6, 7, 9,12, 14, 15, 17, 20, 21,21, 22, 24, 26, 27, 29, 31, 33. What can you conclude about this project?