Your company completed the site work for the South Pointe office complex. The costs are shown in Figure 11-3. The site concrete labor and landscaping were done by subcontractors. The demolition and grubbing and the grading and excavation were done by the company's excavation crew. The company's minimum profit and overhead markup is 15%. Determine the profit generated by the estimator, project management, and the excavation crew on this project.

Job: 411  South Pointe Site Work May 15, 2004

Contract Billed ----------------------Costs----------------------

Code Description Amount to Date Actual Budget Overrun

2050 Demolition & Grubbing                       33,562 35,000 -1,438

2100 Grading & Excavation                         20,500 19,500   1,000

2610 Site Conc.-Labor                                19,200 19,200           0

2620 Site Conc.-Concrete                           9,375    9,900     -525

2700 Landscaping                                       37,500 37,500           0

Job Total                 138,000 128,000 120,137 121,100     -963