You are the project manager of a major IT project in Italy. You review your earned value report and you see that your CPI is .78. What does this mean to you?

A. The project is doing fine. It will be completed on budget.

B. The project is slightly under budget. No corrections are needed.

C. The project is slightly over budget. Corrections are needed.

D. The project is very much over budget. Immediate corrections are needed.