you are preparing a project to lay fiber optic


You are preparing a project to lay fiber optic cable...

You are preparing a project to lay fiber optic cable. The first task is to mobilize the team. You estimate this will take one week and cost $3000. The second task is to lay the cable. This will take three weeks and will cost $45,000. The total length of the cable is 15 miles. The last task, which will take one week, is to Terminate and test the cable. You budget $5000 for this. At the end of the first week, you have completed mobilization, but it cost a total of $4500. At the end of the third week, you have completed five miles of cable at a total cost of $28,000. It takes you a total of 10 weeks to complete the entire project, for a total cost of $65,000.

a. At the end of week 1:
i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?

b. At the end of week 3:
i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?

c. At the end of the project:
i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?

Request for Solution File

Ask an Expert for Answer!!
Project Management: you are preparing a project to lay fiber optic
Reference No:- TGS0472452

Expected delivery within 24 Hours