What is the total manufacturing cost assigned to job


Weaver Company's predetermined overhead rate is $20.00 per direct labor-hour and its direct labor wage rate is $13.00 per hour. The following information pertains to Job A-200:

    
  Direct materials $260
  Direct labor $130

Required:
1.

What is the total manufacturing cost assigned to Job A-200?

  Total manufacturing cost $   
2.

If Job A-200 consists of 60 units, what is the average cost assigned to each unit included in the job?