What is the scheduled completion of the project


Assignment

In this assignment, you will be working through four Activity In Box (AIB) problems. Using the activity, duration, and predecessor information given in this document, you should first construct a network for each project. (Each problem will have its own network.) Once you have constructed the network, please answer the corresponding questions.

Problem 1

The following data were obtained from a project to create a new fitness tracker.

Activity           Duration          Predecessors  
A                     5 Days             ---
B                     6 Days             ---
C                     8 Days             ---
D                     4 Days             A,B
E                      3 Days             C
F                      5 Days             D
G                     5 Days             E,F
H                     9 Days             D
I                       12 Days           G

Step 1: Construct a network diagram for the project

Step 2: Answer the following questions:

a) What is the Scheduled Completion of the Project?

b) What is the Critical Path of the Project?

c) What is the ES for Activity F?

d) What is the LS for Activity G?

e) What is the EF for Activity B?

f) What is the LF for Activity D?

g) What is the float for Activity H?

Problem 2

The following data were obtained from a project to build a sail boat:

Activity           Duration          Predecessors
A                     6 weeks           ---
B                     6 weeks           ---
C                     5 weeks           B
D                     4 weeks           A,C
E                      5 weeks           B
F                      7 weeks           D,E,G
G                     4 weeks           B
H                     8 weeks           F
I                       5 weeks           G
J                       3 week             I

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) Calculate the scheduled completion time.

b) Identify the critical path

c) What is the LF for Activity H?

d) What is the ES for Activity B?

e) What is the LS for Activity E?

f) What is the slack time (float) for Activity D?

g) What is the slack time (float) for Activity G?

Problem 3

The following data were obtained from a project to remodel a kitchen:

Activity           Duration          Predecessors
A                     5 Days             ---
B                     8 Days             ---
C                     6 Days             A
D                     4 Days             C,B
E                      5 Days             A
F                      4 Days             D,E,G
G                     4 Days             B,C
H                     3 Day              G

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) Calculate the scheduled completion time.

b) Identify the critical path(s)

c) What is the EF for Activity G?

d) What is the ES for Activity C?

e) What is the EF for Activity D?

f) What is the LS for Activity E?

g) What is the slack time (float) for Activity H?

Problem 4       

The following data were obtained from a project to design a new software package:

Activity           Duration          Predecessors
A                     4 days                          ---
B                     3 days                          A
C                     5 days                          A
D                     3 days                          A
E                      3 days                          B
F                      2 days                          D
G                     6 days                           C,E,F
H                     3 days                          C,E,F
I                       2 days                         G,H.

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) Calculate the scheduled completion time.

b) Identify the critical path

c) What is the LS for Activity E?

d) What is the LF for Activity D?

e) What is the ES for Activity A?

f) What is the slack time (float) for Activity C?

g) What is the slack time (float) for Activity I?

h) What is the slack time (float) for Activity F?

Format your assignment according to the following formatting requirements:

1. The answer should be typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides.

2. The response also includes a cover page containing the title of the assignment, the student's name, the course title, and the date. The cover page is not included in the required page length.

3. Also include a reference page. The Citations and references should follow APA format. The reference page is not included in the required page length.

Request for Solution File

Ask an Expert for Answer!!
Computer Networking: What is the scheduled completion of the project
Reference No:- TGS02984013

Expected delivery within 24 Hours