What is the least cost method of resolving the conflict


The following data were obtained from a project to design a new software package:

Activity

Duration

Predecessors

Personnel / Cost

A

3 days

--

1 Systems Analyst/$260 day

B

6 days

--

3 Programmers/$200 day each

C

4 days

A

3 Programmers/$200 day each

D

2 days

C

2 Hardware specialists/$230 day each

E

3 days

A

1 Systems Analyst/$260 day

F

2 days

D, E

1 Test Engineer/$300 day

Personnel Available

Quantity

Systems Analysts

1

Programmers

3

Hardware Specialists

2

Test Engineers

2


The software manufacturer has only the above personnel available for the project.Additional personnel can be hired from an agency at an 80% cost premium if needed.

(a) Identify any resource conflicts in the above project. State the activities involved, the time frame of the conflict(s), the personnel in conflict, and the number of people involved.

(b) Note that operations can be split if required: what is the least cost method of resolving the conflict(s), assuming the project duration must not be extended? What additional cost, if any, will be incurred?