What is the actual level of activity


Cadavieco Detailing's cost formula for its materials and supplies is $2,060 per month plus $12 per vehicle. For the month of November, the company planned for activity of 86 vehicles, but the actual level of activity was 46 vehicles. The actual materials and supplies for the month was $2,350.The activity variance for materials and supplies in November would be closest to?