What happens to the restocking level and what is the safety


Question 1. Complete the level production plan using the following information. The only costs you need to consider here are layoff, hiring, and inventory costs. If you complete the plan correctly, your hiring, layoff, and inventory costs should match those given here.

Information Lay off  Hiring  Inventory 
Totals: 25 25 27,690
Costs: $112,500 $87,500 $166,140
Cost of plan:
$366,140
Planning values


Starting inventory:

1,000
Starting and ending workforce:

227
Hours worked per month per worker:

160
Hours per unit:

20
Hiring cost per worker:

$3,500
Layoff cost per worker:

$4.50
Monthly per-unit holding cost:

$6

MONTH FORECASTED SALES SALES IN WORKER HOURS WORKERS NEEDED TO MEET SALES AVERAGE = 252 ACTUAL WORKERS ACTUAL PRODUCTION LAYOFFS   HIRINGS  ENDING INVENTORY
March  1,690







April 1,350







May 1,240







June 1,300







July  1,504







August  1,992







September  2,504







October  2,504







November  3,200







December  3,000







January  2,504







February 2,000







Question 2. Complete the chase production plan, using the following information. The only costs you need to consider here are layoff, hiring, and inventory costs. If you complete the plan correctly, your hiring, layoff, and inventory costs should match those given here.


LAYOFF HIRING INVENTORY
Totals: 250 250 12,000
Costs: $500,000 $750,000 $72,000
Cost of plan:
$1,322,000
Planning values


Starting inventory:

1,000
Starting and ending workforce: Hours 

227
worked per month per worker:

160
Hours per unit:

20
Hiring cost per worker:

$3,000
Layoff cost per worker:

$2,000
Monthly per-unit holding cost:

$6

MONTH FORECASTED SALES SALES IN WORKER HOURS WORKERS NEEDED TO MEET SALES AVERAGE = 252 ACTUAL WORKERS ACTUAL PRODUCTION LAYOFFS   HIRINGS  ENDING INVENTORY
March 1,592







April 1,400







May 1,200







June 1,000







July 1,504







August 1,992







September 2,504







October 2,504







November 3,000







December 3,000







January 2,504







February 1,992







Question 3. The manufacturer of TricoFlexers has agreed to offer Pam a price discount of $5 per unit ($45 rather than $50) if she buys 1,500. Assuming that annual demand is still 40,000, how many units should Pam order at a time?

Question 4. Jimmy's Delicatessen sells large tins of Tom Tucker's Toffee. The deli uses a periodic review system, checking inventory levels every 8 days, at which time an order is placed for more tins. Order lead time is 2 days. Average daily demand is 7 tins, so average demand during the reorder period and order lead time (10 days) is 70 tins. The standard deviation of demand during this same 10-day period is 17 tins. Calculate the restocking level. Assume that the desired service level is 95%.

Question 5. For problem 4, suppose that the standard deviation of demand during the 10-day period drops to 4 tins. What happens to the restocking level? Explain why.

Question 6. For Tom Tucker's Toffee in problem 4, draw a saw-tooth diagram similar to the one in Figure 11.3. Assume that the beginning inventory level is equal to the restocking level and that the demand rate is a constant 7 tins per day.

What is the safety stock level?

What is the average inventory level?

Question 7. The lead time for KraftyCity workbenches is 4 weeks, with a standard deviation of 1.5 weeks, and the average weekly demand is 20, with a standard deviation of 7 work-benches. What should the reorder point be if KraftyCity wants to provide a 95% service level?

Question 8.  Now suppose the supplier of workbenches guarantees KraftyCity that the lead time will be a constant 4 weeks with no variability (i.e., standard deviation of lead time = 0). Recalculate the reorder point, using the demand and service level information in problem 7. Is the reorder point higher or lower? Explain why.

Question 9. Consider the following partially completed master schedule record:

On-hand inventory at end of April: 40
Month  May June

Week 19 20 21 22 23 24 25 26
Forecasted demand 210 210 210 230 225 230 210 210
Booked orders 210 207 209 200 200 187 132 185
Projected ending inventory







Master production schedule 600

675

600
Available to promise





283

a. Complete the projected on-hand inventory calculations and the available-to-promise calculations.

b. Suppose that a customer calls and cancels an order for 50 units in week 25. Which of the following statements are true?

-  The ATP for week 25 will increase by 50 units.

- The projected ending inventory for week 25 will remain the same.

- The ATP for weeks 19 and 22 will be affected.

Question 10. Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled receipts are shown.

WEEK
1 2 3 4 5 6
***A2*** Gross requirments 300 300 300 200 250 250
LT(weeks) = 2 Scheduled receipts
260




Projected ending inventory:360






Net requirements





Min. order = 1 Planned receipts






Planned orders





Question 11. Now suppose the lead time for item A2, shown in problem 6, is three weeks rather than two weeks. Based on this information, can the company support the current gross requirements for the A2? Why? What are the implications of having reliable supplier and manufacturing lead times in an MRP environment?

Question 12. Republic Tool and Manufacturing Company of Carlsbad, California, make a wide variety of lawn care products. One of Republic's products is the Model Number 540 Broadcast Spreader:

2012_Republic Tool and Manufacturing Company.png

Complete the following MRP records. Note the following:

- Republic intends to start assembling 2,000 broadcast spreader kits in weeks 2, 4, and 6.

- The gross requirements for the gear and rotor plate assembly have already been given to you. For the remaining items, you will need to figure out the gross requirements.

- All scheduled receipts, lead times, and beginning inventory levels are shown.

- Note that cotter pins appear twice in the bill of material.

Gear and rotor plate assembly: Lead time = 1 week; Minimum order quantity = 2500

WEEK 1 2 3 4 5 6
Gross requirments
2,000
2,000
2,000
Scheduled receipts





Projected ending inventory:1000





Net requirements





Planned receipts





Planned orders





 

Solution Preview :

Prepared by a verified Expert
Management Theories: What happens to the restocking level and what is the safety
Reference No:- TGS01113031

Now Priced at $50 (50% Discount)

Recommended (99%)

Rated (4.3/5)