What are the total normal costs for the project


Problem: Bob Summers, CEO of Summer Construction has an opportunity to bid on a contract that pays $5500 upon completion, but the contract calls for a late performance penalty of $140 per week for each week that the project is delayed beyond eight weeks.

Activity    Normal Time    Normal Cost    Crash Time    Crash Cost    Immediate Predecessors
A    1    $300    1    $300    -
B    3    $400    1    $470    A
C    2    $350    1    $550    A
D    5    $550    4    $675    A
E    4    $300    3    $375    C
F    2    $450    1    $500    C
G    7    $425    5    $525    C
H    4    $525    2    $625    B,E
I    3    $250    1    $330    D,F
J    1    $300    1    $300   H,G,I

Question 1: Find the crash cost per week for each activity and record the results in the crash table in the table. What are the total normal costs for the project?

Question 2: Which activity would you recommend that Hank crash first, if any?

Question 3: What project duration will minimize project cost?

Question 4: What is the maximum profit that Summers can attain for this project?

Solution Preview :

Prepared by a verified Expert
Other Management: What are the total normal costs for the project
Reference No:- TGS01769298

Now Priced at $25 (50% Discount)

Recommended (96%)

Rated (4.8/5)