Ways to create a new project in ms project


Assignment:

OBJECTIVES

• Introduce learners to some of the basic functionality of Microsoft Project.

• Engage with an activity example to enable self-supported practice and learning.

• Display evidence of a suitably constructed Gantt chart.

• To build confidence for users of the software which can be expanded on to develop further Microsoft Project principles.

PROJECT BRIEF (WIND TURBINE INSTALLATION ACTIVITY):

The Activity comprises the construction of a simple Gantt chart in Microsoft Project. You are tasked to use the 'installation of a wind turbine' work breakdown structure as the basis for doing the following:

1. Create a new project in MS Project.

2. Create a correctly ordered WBS and input this into the task pane within MS Project.

3. Add estimated durations for each activity.

4. Link and indent activities based on their relationships to each other.

5. Add milestones for each phase of the project.

6. Create resources and attach them to work required within the project.

7. Add summary tasks to create a high-level view of the project's phases.

8. Set as a baseline to schedule against.

INSTRUCTIONS:

Step 1. Follow the instructions in this walk through guide for how to complete the activity.

Step 2: Use the supplied word resource for the WBS to copy and paste into project and for a copy of the WBS diagram.

Step 3: Watch the video guide to see if you were able to complete the task correctly.

Walk through steps to follow (in this order to avoid over scheduling yourself):

1. Create a new project. To open up a new blank project file. Go to the File tab and then select the open 'New'.
A selection of options will be presented. Click the 'Blank Project' option and a new blank project will be created for you.

2. Change to Automatic Scheduling. On the bottom left hand corner of your screen it will show you your current scheduling mode (Automatic or Manual).

For the purposes of this exercise we require it to be switched to 'Automatic' if not already at this setting. To do this, go again to the File Tab, Select 'Options', it will bring up a pop like the one illustrated below. Go down a click the 'Schedule' on the left hand side menu and towards the bottom of the options there is a choice to change the 'New Tasks Created' to be either 'Manually Scheduled' or 'Auto Scheduled'. Change it so that it is now set to 'Auto Scheduled' then click 'OK'.

3. Import the data. To have a WBS to work from copy and paste into your Gantt chart the numbered dissertation task list as found in the assignment brief. This will then populate the task pane with the required tasks. If you didn't have any data to import you would have to enter each task individually by hand. Make sure you paste into the 'Task Name' column only.

4. Review / change working hours. The work days should automatically be set to have Saturday and Sunday off so you shouldn't be default need to change anything for the working schedule on this calendar. To review go to the 'Project' tab and then click the icon named 'Change Working Time' Review the Calendar and select 'Options' to make further changes.

5. Change the duration values. Go ahead and start changing the values of each task away from the default value of 1 day. There are no right/wrong values it is just an exercise to get you familiar with changing them manually but think about how realistic your durations may be.
Remember the short cuts you can use, typing 111 will change the task duration to 1 hour. ld will change to 1 day and lw will change it to 1
As you change the durations you should see the difference reflected in the Gantt.

6. Set your milestones. Think where your milestones will go in relation to the WBS. Review the hand out diagram and place the milestones according to how each group is ID numbered. To enter a milestone you need to select a task one space below where you want to place your milestone, as it will be inserted above the highlighted area.

A milestone is characterised by the diamond on the Gantt and always has a value of zero. If you change the value away from zero it then becomes something other than a milestone. Make sure that you name the milestone you have created.

Give your milestone a name and it should have 0 days as the Duration. It should be represented in the Gantt as a black diamond with a date attached if inserted correctly.

7. Highlight all the tasks and link together. The relationships that tasks have with each other are an important feature of your Gantt. To link them together you do this by highlighting all the tasks required (in this scenario them all) and then pressing the link icon from the menu (looks like a little chain).

If done correctly it should show that the start/finish dates have been altered so that they are not running on the same date anymore. There should be a populated list of numbers within the predecessors column and the time line should have tasks linked together with arrowed lines to reflect their current relationship.

8. Add resources. Now having scheduled activities which have a relationship to each other we are in the position to add resources to these tasks. From the 'Gantt Chart' button select 'Resource View' then pick the 'Resource Sheet'. On the resource sheet add a resource and set the pay amounts for standard and overtime rates (again no correct amount put what you determine is realistic).

Like an Excel spreadsheet, manually enter in any applicable resources (people, equipment etc) ensuring that you have identified the type of work and given a rate of pay for that resource. Click the Gantt Chart button to return to the Gantt
view.

9. Assign resources. Having created a bank of resources to select from we now need to attach them to the correct points in our WBS. To do this we can highlight all the tasks again and then press the 'Assign Resource' button. From the pop up box that appears highlighted your desired resource and click the 'Assign' button. Your name should now appear beside all the tasks you are engaged in throughout the project.

A popup menu should appear. Select the resource you want, highlight them and then click 'Assign'. This should attach the resource to the highlighted tasks and should show up with the resource name in the Gantt.

10. Set summary tasks. These are linked to your WBS and is a good house keeping exercise to group all those tasks in the same level together. Select all the tasks that are related (remember to include the milestones) and then click the summary button and above the highlighted tasks a new summary of those tasks will have been created and the tasks grouped together.

Select the phase of the WBS you want to group together by highlighting them. Go to the 'Task' tab and the click the 'Summary' icon. You will be asked to give a name of the Summary, rename it and repeat for the other phases. By doing this you can hide sections of the WBS and see information at both a top level or click through to view at a more detailed level.

11. Review statistics. Should you want to provide a breakdown of data for a meeting or to have a summary of statistics this can be done by generating a report. Within the 'Project' tab go to the 'Reports' icon and look through the selected reports to see how differently the information from your project can be displayed and analysed.

12. Set a baseline and get to work. With your project schedule complete you can now go to the 'Project' tab and select the 'Set Baseline' button to create a snap shot of your expected project schedule. As you go ahead with your project, you will see a visual indicator for how far ahead/behind you are to your original baseline as you update the schedule.

Attachment:- Prepare a project on wind turbine.rar

Solution Preview :

Prepared by a verified Expert
Project Management: Ways to create a new project in ms project
Reference No:- TGS02023935

Now Priced at $40 (50% Discount)

Recommended (93%)

Rated (4.5/5)