Using a spot exchange rate of 125 as the forecast fx rate


Zimmer, a manufacturer of modular rooms, plans to expand its operations in Landshut, Germany. The expansion will cost $14.5 million and is expected to generate annual net cash flows of €2.15 million for a period of 12 years and then the operation will be sold for €1 million (net of taxes). The cost of capital for the project is 14%. Using a spot exchange rate of $1.25/€ as the forecast FX rate for the euro for the term of the project, compute the NPV of this expansion project.