The total amount of actual task time across all four


1. A production line has four workstations and a 50-second cycle time. The total amount of actual task time across all four workstations is 170 seconds. What is the idle time? The percent idle time? The efficiency delay?

2. Polar Containers makes high-end coolers for camping.The total task time needed to make a cooler is 360 seconds, with the longest individual task taking 50 seconds. Polar Containers would like to set up a line capable of producing 50 coolers per 8-hour day. What is the take time? What is the maximum output per day?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: The total amount of actual task time across all four
Reference No:- TGS02717561

Expected delivery within 24 Hours