The production manager for the coory soft drink company is


The production manager for the Coory soft drink company is considering the production of two kinds of soft drinks: regular and diet.

Two of her limited resources are production time (8 hours = 480 minutes per day) and syrup (1 of the ingredients), limited to 675 gallons per day.

To produce a regular case requires 2 minutes and 5 gallons of syrup, while a diet case needs 4 minutes and 3 gallons of syrup.

Profits for regular soft drink are $3.00 per case and profits for diet soft drink are $2.00 per case.

Which of the following is not a feasible production combination?