The producer knows there is a big order or order contract


A producer of pottery is considering the addition of a new plant to absorb the backlog of demand that now exists. The primary location being considered will have the following cost structures as shown in the table.

The producer knows there is a big order or order contract that will be awarded by the giant retail WalWal. The producer is not certain as what capacity production is to produce. It all depends on WalWal's contract.

The producer has also been informed, the first batch of pottery is required to ship in a very tight time frame from the first production run. The producer decides to plan ahead and select the best production process to set up for manufacturing.

Process 1
Process 2
Process 3
Ann. Fixed Cost $
8,867
14,369
6,251
variable cost $/unit
0.71
0.59
1.02

The producer wants you to help them to identify at what range of production Q (quantity) is Best to adopt Process 1, Process 2, and Process 3.

Note: To sepcify annual Q range, use 1234 < Q <= 5678.

Questions:

a) The range of annual Q for which Process 1 is best to use is:

b) The range of annual volume for which Process 2 is best to use is:

c) The range of annual volume for which Process 3 is best to use is:

Request for Solution File

Ask an Expert for Answer!!
Operation Management: The producer knows there is a big order or order contract
Reference No:- TGS02717453

Expected delivery within 24 Hours