the following activities are part of a project to


The following activities are part of a project to be scheduled using CPM:

Activity Intermediate Predecessor Time (WEEKS)
A 6
B A 3
C A 7
D C 2
E B,D 4
F D 3
G E,F 7

a. Draw the network.

b. What is the critical path?

c. How many weeks will lit take to complete be project?

d. How much slack does the activity B has?

Request for Solution File

Ask an Expert for Answer!!
Project Management: the following activities are part of a project to
Reference No:- TGS0472315

Expected delivery within 24 Hours