The average time per cycle was 107 minutes and the standard


Problem

An analyst has timed a metal-cutting operation for 50 cycles. The average time per cycle was 10.7 minutes, and the standard deviation was 1.20 minutes for a worker with a performance rating of 133 percent.

Assume an allowance of 15 percent of job time.

Find the standard time for this operation. (Do not round intermediate calculations. Round your final answer to 2 decimal places.)

Solution Preview :

Prepared by a verified Expert
Operation Management: The average time per cycle was 107 minutes and the standard
Reference No:- TGS02716180