Prepare a schedule that discloses the individual cost


Case Scenario:

On January 1, 2007, George Solti Corporation purchased for $600,000 a tract of land (site number 101) with a building. Solti paid a real estate broker's commission of $36,000, legal fees of $6,000, and title guarantee insurance of $18,000. The closing statement indicated that the land value was $500,000 and the building value was $100,000. Shortly after acquisition, the building was razed at cost of $54,000.

Solti entered into a $3,000,000 fixed-price contract with Slatkin Builders, Inc. on March 1, 2007, for the construction of an office building on land site number 101. The building was completed and occupied on September 30, 2008. Additional construction cost were incurred as follows:

Plans, specifications, and blueprints $21,000

Architects' fees for design and supervision 82,000

The building is estimated to have a 40-year life from date to completion and will be depreciated using the 150% declining balance method.

To finance construction costs, Solti borrowed $3,000,000 on March 1, 2007. The loan is payable in 10 annual installments of $300,000 plus interest at a rate of 10%. Solti's weighted-average amounts of accumulated building construction expenditures were as follows:

For the period March 1 to December 31, 2007 $1,200,000
For the period Jan 1 to Sept. 30, 2008 1,900,000

Instructions:

Q1. Prepare a schedule that discloses the individual costs making up the balance in the land account in respect of land site number 101 as of September 30, 2008.

Q2. Prepare a schedule that discloses the individual cost that should be capitalized in the office building account as of September 30, 2008. Show supporting computations in good form

(AICPA adapted)

Solution Preview :

Prepared by a verified Expert
Finance Basics: Prepare a schedule that discloses the individual cost
Reference No:- TGS01802156

Now Priced at $25 (50% Discount)

Recommended (94%)

Rated (4.6/5)