For each of the following network diagrams determine both


For each of the following network diagrams, determine both the critical path and the expected project duration. The numbers on the arrows represent expected activity times.

a. Activity-on-arrow diagram

The critical path is (Click to select)1-3-7-8-91-3-6-9-11-121-2-5-8-10-121-2-5-7-8-91-2-4-7-10-12.
The expected project duration is.

b. Activity-on-node diagram

The critical path is (Click to select)1-2-5-6-8-91-2-5-7-8-91-2-4-6-8-91-3-7-8-91-3-6-9-11-12.
The expected project duration is.

c. Activity-on-arrow diagram

The critical path is (Click to select)1-3-6-13-161-2-5-12-161-3-7-14-161-4-8-10-11-15-161-4-8-9-10-11-15-16.
The expected project duration is.

Request for Solution File

Ask an Expert for Answer!!
Computer Networking: For each of the following network diagrams determine both
Reference No:- TGS01106224

Expected delivery within 24 Hours