Process times for all jobs are one hour. Changeovers between families require four hours. Thus, the completion time for job 1 is 5, for job 2 is 6, for job 3 is 11, and so on.

Job

Family Code

Due Date

1

1

5

2

1

6

3

2

12

4

2

13

5

1

13

6

1

19

7

1

20

8

2

20

9

2

26

10

1

28

1. Compute the total tardiness of the sequence.

2. How many possible sequences are there?

3. Find a sequence with no tardiness.

 