Compute the plantwide overhead rate that would be used in


Problem - Sandstorm Manufacturing Inc. makes two types of industrial component parts-the LE100 and the UL600. It annually produces 120,000 units of LE100 and 25,000 units of UL600. The company's conventional cost system allocates manufacturing overhead to products using a plantwide overhead rate and direct labor dollars as the allocation base. Additional information relating to the company's two product lines is shown below:


LE100

UL600

Total

Direct materials

$720,000

$357,000

$1,077,000

Direct labor

$240,000

$100,000

$340,000

The company is considering implementing an activity-based costing system that distributes all of its manufacturing overhead to four activities as shown below:

Activity Cost Pool
(and Activity Measure)

Manufacturing Overhead

Activity

LE100

UL600

Total

Machining (machine-hours)

$400,000

36,000

135,000

171,000

Setups (setup hours)

300,000

150

600

750

Product-level (number of products)

200,500

2

2

4

General factory (direct labor dollars)

120,000

$240,000

$100,000

4340,000

Total manufacturing overhead cost

$1,020,500




Required:

1-a. Compute the plantwide overhead rate that would be used in the company's conventional cost system.

1-b. Using the plantwide rate, compute the unit product cost for each product.

2-a. Compute the activity rate for each activity cost pool.

2-b. Using the activity rates, compute the unit product cost for each product.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Compute the plantwide overhead rate that would be used in
Reference No:- TGS02705552

Now Priced at $25 (50% Discount)

Recommended (90%)

Rated (4.3/5)