Calculate the cost of necklaces completed during january


Question:

(Hybrid costing) Pat Koontz makes necklaces from glass beads, metal beads, and natural beads. After reading about hybrid costing, she realized that the different types of necklaces did not cost the same amount of money to make, even though they took the same amount of time and effort to assemble. Koontz developed the following standard costs for each type of necklace:


Glass

Metal

Natural

Beads

$24

$15

$ 7

Direct labor (1.5 hours)

15

15

15

Overhead (based on 1.5 hours)

8

8

8

Total

$47

$38

$30

Koontz began 2010 with no beginning WIP Inventory after she experienced an extreme holiday rush. During January, 130 necklaces were started: 70 were glass, 25 were metal, and 35 were natural. At the end of January, 25 necklaces were not yet complete: 5 glass,13 metal, and 7 natural. The stage of completion for each cost component for the 25 unfinished necklaces was as follows:

Material

100% complete

Conversion

60% complete

a. Calculate the cost of necklaces completed during January.

b. Calculate the cost of necklaces in ending WIP Inventory.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Calculate the cost of necklaces completed during january
Reference No:- TGS02044015

Now Priced at $10 (50% Discount)

Recommended (93%)

Rated (4.5/5)