Calculate the budgeted manufacturing overhead rate


Problem

Maynard Company uses normal costing. It allocates manufacturing overhead costs using a budgeted rate per? machine-hour. The following data are available for 2014?:

Budgeted manufacturing overhead costs $4,150,000
Budgeted machine-hours 166,000
Actual manufacturing overhead costs $3,990,000
Actual machine-hours 161,000

1. Calculate the budgeted manufacturing overhead rate.
2. Calculate the manufacturing overhead allocated during 2014.
3. Calculate the amount of under- or overallocated.