Busm4407 advanced project risk management assignment -


Advanced Project Risk Management Assignment -

Aim: The aim of this assignment is to:

  • demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree
  • schedule a project using Oracle Primavera P6.

Decision Tree/Precision Tree -

A contractor working on an outdoor construction project in a coastal area is reviewing progress on August 1. If normal progress is maintained and no time is lost due to hurricanes, the job will be completed on August 31. However, due to the poor weather conditions in the area after August 16, there will be only a 40 percent chance of finishing on time. It is estimated that there is a 40 percent chance of a minor hurricane, which will cause a delay of 6 days. There is a 20 percent chance of a major hurricane, which will cause a delay of 12 days. It must be decided now whether to speed up the work from August 2 at an additional cost of $150 per day and finish the project on August 16 (i.e. in 15 days) or take the risk that a hurricane might occur in the project area before 31st August. In the event of a hurricane, the cost of the project delay would be $900 per day for first 6 days and $1200 per day for next 6 days.

a) Develop a decision tree for the above problem (you can use MS Word).

b) Using the Expected Monetary Value (EMV) technique to find out the best possible option. Show your workings.

c) Provide the solution to the above question using precision tree and provide related screen shots or print in word file.

Primavera Planner P6 -

You have recently been made a part of a team who is working to establish a "Project Office" or Project Management Office (PMO) in a large organisation. There are various briefing meetings that have already been held. As a result of those meetings a WBS, activity definitions activity durations and activity relationships all have been defined and summarised in an Excel Table (attached). The management has decided to use Primavera Planner P6 for scheduling of this project. You have learnt great deal about using Primavera in your uni days and have therefore raised your hand to take up this responsibility. All the team is now counting on your skills to put together a project plan in Primavera Planner P6.

Assume the project start date and working time. Also use appropriate Australian holidays/non- working days in your schedule. State these upfront.

You should include the following in your submission:

a. Printed Gantt Chart and Project Network (pdf)

b. Printed Gantt Chart Critical Path only (pdf)

c. XER file with file saved using the following format "student_id_last name_first_name.xer (example 1234567_bloggs_joe.xer).

Attachment:- Assignment Files.rar

Request for Solution File

Ask an Expert for Answer!!
Risk Management: Busm4407 advanced project risk management assignment -
Reference No:- TGS02915348

Expected delivery within 24 Hours