At a required return of 8 percent what is the npv of the


A project that provides annual cash flows of $2,400 for nine years costs $9,900 today.

At a required return of 8 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

NPV            $

At a required return of 24 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

NPV            $

At what discount rate would you be indifferent between accepting the project and rejecting it? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)

Discount rate             %

Request for Solution File

Ask an Expert for Answer!!
Financial Management: At a required return of 8 percent what is the npv of the
Reference No:- TGS02809474

Expected delivery within 24 Hours