Assign jobs so that total time is minimized


Question: In a job shop operation, four jobs may be performed on any of four machines. The hours required for each job on ach machine are presented in the following table. The plant supervisor would like to assign jobs so that total time is minimized. Use the assignment method to find the best solution.

             Machine

Job    W   X   Y   Z

A12    10  14  16  13
A15    12  13  15  12
B2      9   12   12  11
B9     14  16   18  16