Although the use of these processes can vary what is the


The PMBOK includes 47 different project management processes.

Although the use of these processes can vary, what is the typical sequence of the applying the processes within the process groups?

Initiating, Planning, Executing, Monitoring & Controlling, and Closing.

Monitoring & Controlling, Initiating, Executing, Planning, and Closing Initiating, Planning, Executing, and Closing. The correct answer is not listed.