A project to build a new bridge seems to be going very well


A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low.

A major milestone has been reached where the first two activities have been totally completed and the third activity is 55% complete. the planners were only expecting to be 46% through the third activity at this time. the first activity involves prepping the site for the bridge. It was expected to cost $1330000 and it was done for only $1295000. the second activity was the pouring of the concrete.

This was expected to cost $11000000 but was actually done for $11200000. the third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8550000. To date they have spent $6900000 on the superstructure.

Calculate the cost and schedule variance and the schedule and cost performance indexes for the project.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A project to build a new bridge seems to be going very well
Reference No:- TGS02717747

Expected delivery within 24 Hours