You are considering two mutually exclusive projects at what


You are considering two mutually exclusive projects, A and B.

Project A costs $65,000 and generates cash flows of $11,000 for 10 years.

Project B costs $100,000 and generates cash flows of $10,000 per year for five years and then a cash flow of $105,000 in year 6. There are no cash flows after year 6 for Project B.

Report rates in percentage form to two decimal places i.e. 10.03% not 10%

1) At what discount rate would make you indifferent between choosing one project or another?

2) Which project would you ACCEPT if your discount rate was 9%?

A. project A B. project B C.Both Project A and B    D.Neither Project A or B

3) Which project would you ACCEPT if your discount rate was 5%?

A. project A B. project B C.Both Project A and B    D.Neither Project A or B

4) What is the highest discount rate in which you can still produce a non-negative NPV?