Which phase of project management is quality hospital in


Problem: Quality Hospital is regularly assessing the planned activities and their timeline for the implementation of the new electronic health record. The Project Manager is changing some things in order to bring the project back on track. Which phase of project management is Quality Hospital in? 1. Planning 2. Execution 3. Initiation 4. Monitoring and controlling

 